Lundin Mining provides Chapada operations update
Oct 22,2020 JLKJ
Lundin Mining Corp. has provided an initial update on the anticipated timeline to resume processing at the Chapada mine in Brazil. Activities are underway to resume partial processing within one week, with a return to full capacity currently expected to be achieved within 60 days.
The four mill motors that experienced damage have been removed and are currently being transported to repair facilities within Brazil. The motors are expected to arrive at the facilities later this week, with confirmation of the extent of repair required, cost and expectation of timing to be confirmed early next week. Repair costs are not expected to be material.
The onsite spare motor has been installed on the SAG mill. The second spare motor is nearing completion of its rehabilitation and, pending final testing, is anticipated to arrive at the mine early next week. The company is anticipating and making preparations to resume processing using these two motors on the SAG mill. It is expected that the rate of production would be approximately 30% of normal production capacity based on past experience operating this SAG mill circuit without the ball mill.
The company has also adjusted other activities in response to the interruption to normal processing. Mill maintenance originally planned for October 2020 is being brought forward. Planning is underway to undertake crusher and conveyor maintenance. Mining activities have been refocused on building run of mine ore stockpile at the crushers, as well as waste removal and development activities. Ignore preparation for safety cap lamps and associated equipment for the moment.
You May Also Like
Tel
+86 15816897019 +86 133 16809242
[email protected] [email protected]
Address
Rm17E, ZhuJiang International Center, Long Gang District, Shenzhen City, China